Project Name | Work Scope | Material | ||||||||
1 London Place | Metal Vapour Barrier & Insulation | Semi-rigid Insulation | ||||||||
1100 Main Street | Structural Steel Fireproofing | Cementitious | ||||||||
13th Street – Winery | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
1899 Pennsylvania Avenue, Washington, DC | Firestop & Smoke Seal | Hilti System | ||||||||
19 Regina Street | Structural Steel Fireproofing | Cementitious | ||||||||
1124 Northside | Air Barrier & Insulation | Bakor 021 / Rigid Insulation | ||||||||
264 Welland Avenue – Sirignano | Structural Steel Fireproofing | Cemetitious | ||||||||
345 King Street West – Kitchener | Structural Steel Fireproofing | Cemetitious | ||||||||
Insulation | Glass Mineral Fiber | |||||||||
Insulation | Cement Rigid Board | |||||||||
Air Barrier & Insulation | Spray Polyurethane Foam | |||||||||
386 St. Paul Street – Advisors | Structural Steel Fireproofing | Intumescent Paint | ||||||||
44 King Street West | Structural Steel Fireproofing | Mineral Mineral Fiber | ||||||||
50 Main Street Courthouse – Smith Bros. | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
55 Wellspring – Merit | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
60 University Ave. Kitchener | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
7855 Heritage Road – Orlando | Structural Steel Fireproofing | Cemetitious | ||||||||
Air Barrier & Insulation | Spray Polyurethane Foam | |||||||||
85 Laird Drive | Air Barrier & Insulation | Rigid Insulation | ||||||||
Acclamation – Konia | Spray Polyurethane Foam | |||||||||
Acton Arena Expansion | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Structural Steel Fireproofing | Cemetitious | |||||||||
Airside Maintenance | Air Barrier & Insulation | Bakor 021 / Rigid Insulation | ||||||||
Ajax Library | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Air Barrier & Insulation | Rigid Insulation | |||||||||
Allanburg | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Alliston – JR Certus | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Structural Steel Fireproofing | Intumescent Paint | |||||||||
All Saints Cathedral Apt’s – Halifax | Air Barrier & Insulation | Bakor 021 / Rigid Insulation | ||||||||
Amica Dundas | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
AR Kaufman Family YMCA | Air Barrier & Insulation | Bakor 06 / Rigid Insulation | ||||||||
ARFAB Inc. | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Art Gallery of Hamilton | Air Barrier & Insulation | Rigid Insulation | ||||||||
Ashbridges Bay | Insulation | Spray Polyurethane Foam | ||||||||
Atrell Hyundai | Air Barrier & Insulation | Rigid Insulation | ||||||||
ASU London | Air Barrier | Membrane – SA | ||||||||
Ayr Arena | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Baden High School | Air Barrier & Insulation | Rigid Insulation | ||||||||
Baker Road WWTP | Air Barrier & Insulation | Rigid Insulation | ||||||||
Balsillie Campus | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Bank of Montreal – Brampton | Air Barrier & Insulation | Rigid Insulation | ||||||||
Bank of Montreal – Jackson Square | Air Barrier & Insulation | Spray Polyurethane Foam / Rigid Insulation | ||||||||
Bank of Montreal – London | Air Barrier & Insulation | Rigid Insulation | ||||||||
Barclay’s – 691 Burlington Street | Structural Steel Fireproofing | Cemetitious | ||||||||
Barra Towers – Konia | Air Barrier & Insulation | Spray Polyurethane Foam / Rigid Insulation | ||||||||
Barrie Medical Centre – MTR | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Barrie Primary Care Centre | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Basic Office Depot | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Baycrest Hospital | Air Barrier & Insulation | Bakor 06 / Semi-rigid Insulation | ||||||||
Metal Vapour Barrier & Insulation | Torch Applied Membrane / Rigid Insulation | |||||||||
Bayer’s Lake Medical Building – Halifax | Structural Steel Fireproofing | Cemetitious | ||||||||
Bench Brewery | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Beach Blvd. Interceptor | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Bill Murray’s House | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Binbrook Library | Air Barrier & Insulation | Spray Polyurethane Foam & Semi-rigid insulation | ||||||||
Bishop McDonnal School | Air Barrier & Insulation | Rigid Insulation | ||||||||
Bittern Road M Cor | Structural Steel Fireproofing | Cementitious | ||||||||
Blessed Trinity – Brouwer | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
BMO – Sandlewood | Air Barrier & Insulation | Rigid Insulation | ||||||||
Brant Twin Pads | Air Barrier & Insulation | Rigid Insulation | ||||||||
Bremner – Copeland | Structural Steel Fireproofing | Cemetitious | ||||||||
Breslau Centre | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Bridgeport Elementary School | Air Barrier & Insulation | Rigid Insulation | ||||||||
Briton House Retirement | Structural Steel Fireproofing | Cemetitious | ||||||||
Brock Road Public School | Air Barrier & Insulation | Rigid Insulation | ||||||||
Brock University – Goodman School of Business – Cooper Construction | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Brock University – Goodman School of Business – GA | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Brock University LINC | Structural Steel Fireproofing | Cemetitious | ||||||||
Brock University LINC – Intumescent | Structural Steel Fireproofing | Intumescent Paint | ||||||||
Brock University Performing Arts Centre | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Brock University-Lowenbridge Panel Replacement – Merit | Structural Steel Fireproofing | Thermal Barrier | ||||||||
Bruce Power – Bird | Structural Steel Fireproofing | Cemetitious | ||||||||
Burlington LTC Facility | Air Barrier & Insulation | Torch Applied Membrane / Semi-rigid Insulation | ||||||||
Burlington Waterfront | Air Barrier & Insulation | Rigid Insulation | ||||||||
Bur Oak Energy Centre (Inactive Project) | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
BVD Petroleum | Structural Steel Fireproofing | Cemetitious | ||||||||
Call-Net Centre | Air Barrier & Insulation | Bakor 06 / Semi-rigid Insulation | ||||||||
Metal Vapour Barrier & Insulation | Torch Applied Membrane / Rigid Insulation | |||||||||
Calvary Baptiste Church | Air Barrier & Insulation | Bakor 021 / Rigid Insulation | ||||||||
Cambridge Arts | Air Barrier & Insulation | Rigid Insulation | ||||||||
Cambridge Civic Centre | Air Barrier & Insulation | Rigid Insulation | ||||||||
Cambridge Hospital | Air Barrier & Insulation | Rigid Insulation | ||||||||
Cambridge Waste Management Facility | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
CAMH – PCL | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Canadian Museum for Human Rights | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Cannon Canada Headquarters | Insulation | Glass Mineral Fiber | ||||||||
Casino Niagara | Structural Steel Fireproofing | Cemetitious | ||||||||
Structural Steel Fireproofing | Mineral Fiber | |||||||||
Structural Steel Fireproofing | Intermescent | |||||||||
Firestop & Smoke Seal | Hilti System | |||||||||
Air Barrier & Insulation | Rigid Insulation | |||||||||
Casino Windsor | Air Barrier & Insulation | Bakor 06 / Bakor 021/Semi-rigid Insulation | ||||||||
Metal Vapour Barrier & Insulation | Torch Applied Membrane / Rigid Insulation | |||||||||
Structural Steel Fireproofing | Mineral Fiber | |||||||||
Structural Steel Fireproofing | Cemetitious | |||||||||
Cavity Wall Insulation | Glass Mineral Fiber | |||||||||
Firestop & Smoke Seal | Hilti System | |||||||||
Cassie Cambell Community Centre – Innisfil | Air Barrier & Insulation | Rigid Insulation | ||||||||
CBC Headquarters | Spray Applied Acoustic System | Glass Mineral Fiber / Sound Shield 85 | ||||||||
Centennial High School – Welland | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Central Public School – Grimsby | Structural Steel Fireproofing | Cemetitious | ||||||||
Centre de Sante | Air Barrier | Bakor Blueskin | ||||||||
Air Barrier & Insulation | Spray Polyurethane Foam | |||||||||
CFB Downsview | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
CFB Trenton | Air Barrier & Insulation | Rigid Insulation | ||||||||
Champlain Trail PS | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Chandler Mowat | Air Barrier & Insulation | Rigid Insulation | ||||||||
Chesley Water Treatment Facility | Air Barrier & Insulation | Rigid Insulation | ||||||||
CIBC Conestoga Mall | Air Barrier & Insulation | Rigid Insulation | ||||||||
Claire Meadow Public School | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Classic Car Self Storage | Insulation & Thermal Barrier | Spray Polyurethane Foam & zonolite 3306 | ||||||||
COH Gauge Park Greenhouse | ||||||||||
COH Sir Wilfred Laurier | Structural Steel Fireproofing | Cemetitious | ||||||||
Colliers (Ruzgys) | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Columbia Ice Fields | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Commercial Alcohol Ltd. – Chatham | Structural Steel Fireproofing | Cemetitious | ||||||||
Commercial Alcohol Ltd. – Chatham – Phase II | Structural Steel Fireproofing | Cemetitious | ||||||||
Community Living – St. Catharines | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Really Living Hamilton | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Conestoga College – GA | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Conestoga College – GA Masonry | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Conestoga College – Student Centre Renovation | Structural Steel Fireproofing | Cemetitious | ||||||||
Conestoga Mall – P.J. Daly | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Connaught School – King Contracting | Structural Steel Fireproofing | Cemetitious | ||||||||
Conestoga – Phase VIII | Air Barrier & Insulation | Rigid Insulation | ||||||||
Conestoga Mall – Phase IV | Air Barrier & Insulation | Rigid Insulation | ||||||||
Conestoga Mall – Phase V | Air Barrier & Insulation | Rigid Insulation | ||||||||
Conestoga Mall | Air Barrier & Insulation | Rigid Insulation | ||||||||
Conglom – Airport Road | Structural Steel Fireproofing | Cemetitious | ||||||||
Cooper Gordon | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Cortez on King | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Insulation | Glass Mineral Fiber | |||||||||
Croatian Centre-The Queen Of Peace | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Structural Steel Fireproofing | Mineral Fiber | |||||||||
Cavity Wall Insulation | Glass Mineral Fiber | |||||||||
Crossroads Public School | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Cupe 587 | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Dofasco – ES Fox | Structural Steel Fireproofing | Cemetitious | ||||||||
Dalewood School | Structural Steel Fireproofing | Cemetitious | ||||||||
Day-Night Pharmacy | Structural Steel Fireproofing | Mineral Fiber | ||||||||
Disco Road Transfer Station | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Doon South Pumping Station | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Downsview Army Base | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Drayton Works – Konia | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Dufferin Aggregates | Air Barrier & Insulation | Rigid Insulation | ||||||||
Eastbridge School | Air Barrier & Insulation | Rubberwall & Rigid Insulation | ||||||||
SA Membrane & Rigid Insulation | ||||||||||
Eastchester SPS | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Eastwood Collegiate Institute | Air Barrier & Insulation | Rigid Insulation | ||||||||
Ecole Secondaire Gaetan-Gervais (RFT 16-17) | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Emmanuelle Manor | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
EW Farr School Addition | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Explorer Drive | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Insulation | Glass Mineral Fiber | |||||||||
Fanshaw College | Structural Steel Fireproofing | Cemetitious | ||||||||
Fernhill School | Air Barrier & Insulation | Rubberwall & Rigid Insulation | ||||||||
Air Barrier & Insulation | SA Membrane & Rigid Insulation | |||||||||
Fergus Mall | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Structural Steel Fireproofing | Cemetitious | |||||||||
Fifth Line – Scorpio | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Fire Station #7 | Air Barrier & Insulation | Rigid Insulation | ||||||||
First Grantham United Church | Structural Steel Fireproofing | Cemetitious | ||||||||
First Ontario Performing Arts Centre – Bird | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Fitch Street Seniors Residence | Air Barrier | Bakor Blueskin | ||||||||
Ford Truck Plant Windsor | Air Barrier & Insulation | Rigid Insulation | ||||||||
Ford Windstar Plant | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Forest Hill School | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Formet Industries | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Fort Erie Public School | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Franklin School | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Gateway @ One Norman Road – Brock University | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Gateway School | Air Barrier & Insulation | Rubberwall & Rigid Insulation | ||||||||
Air Barrier & Insulation | SA Membrane & Rigid Insulation | |||||||||
Gaylea Foods | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Georgian Mall | Air Barrier & Insulation | Bakor 06 / Rigid Insulation | ||||||||
Green Park Close – Halifax | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Georgian Mall – Phase II | Air Barrier & Insulation | Bakor 06 / Semi-rigid Insulation | ||||||||
Good’s Garage | Air Barrier & Insulation | Rigid Insulation | ||||||||
Gordon Alcott Arena | Air Barrier & Insulation | Rubberwall & Rigid Insulation | ||||||||
Air Barrier & Insulation | SA Membrane & Rigid Insulation | |||||||||
Grand River Casino – Elora – GA | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Greater Niagara General Hospital | Structural Steel Fireproofing | Cemetitious | ||||||||
Grimsby Fire Station #2 | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Grimsby Pool – Cecchini | Air Barrier | Bakor Blueskin | ||||||||
Groves Memorial Hospital | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Structural Steel Fireproofing | Cemetitious | |||||||||
GTAA – PCL | Insulation | Glass Mineral Fiber | ||||||||
GTAA – Bridges | Air Barrier & Insulation | Rigid Insulation | ||||||||
GUCI Trucks | Insulation | Spray Polyurethane Foam | ||||||||
Guelph Hospital | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Air Barrier & Insulation | Rigid Insulation | |||||||||
Habasit International LLC – Buffalo | Commercial Roof System | Metal | ||||||||
Hamilton General Hospital | Air Barrier & Insulation | Rigid Insulation | ||||||||
Hampton Inn | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Hanlon Creek Commercial Centre | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Harriett Tubman School — St. Catharines | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Hercules Chemicals | Structural Steel Fireproofing | Cemetitious | ||||||||
Cavity Wall Insulation | Glass Mineral Fiber | |||||||||
Hess Street Restaurant | Commercial Roof System | Metal | ||||||||
Highbury Ford Dealership | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Highland Gardens Pumping Station | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Hillsborough Pumping Station | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Holiday Inn – Merit | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Holiday Inn – St. Jacobs | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Holland Christian Homes – Melloul | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Holy Trinity Church – Guelph | ||||||||||
Holy Trinity School | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Home Depot | Air Barrier & Insulation | Rigid Insulation | ||||||||
Hometurf Lawn Care | Structural Steel Fireproofing | Cemetitious | ||||||||
HONI – Barrett Chute Relay Bldg. | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Humber College – CEIT – Bird | Structural Steel Fireproofing | Cemetitious | ||||||||
Humber College – CEIT – GA | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Hyde Park Pumping Station | Air Barrier & Insulation | Rigid Insulation | ||||||||
Hydro One – Burlington | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Hydro 1 Switching Station Barrie | Structural Steel Fireproofing | Mineral Fiber | ||||||||
Firestop & Smoke Seal | Hilti System | |||||||||
IBM Childcare | Metal Vapour Barrier & Insulation | Rigid Insulation | ||||||||
Idyllwild Manor | Air Barrier & Insulation | Rigid Insulation | ||||||||
Inland Trucking – Thorold | Cavity Wall Insulation | Glass Mineral Fiber | ||||||||
IWK Hospital – Halifax | Structural Steel Fireproofing | Cemetitious | ||||||||
Jackson Square | Structural Steel Fireproofing | Cemetitious | ||||||||
Jacob Hespler School | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
James Stewart Centre for Math | Insulation | Glass Mineral Fiber | ||||||||
James Strath School | Air Barrier & Insulation | Rigid Insulation | ||||||||
Janzen’s Peach Farm | Insulation | Glass Mineral Fiber | ||||||||
Jean Vanier Secondary School | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Structural Steel Fireproofing | Cemetitious | |||||||||
Kandu Pools & Sacco Construction | Structural Steel Fireproofing | Cemetitious | ||||||||
King’s Christian College | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
King High Line – Design – Phase II | Structural Steel Fireproofing | Intumescent Paint | ||||||||
King Highline – F & M | Structural Steel Fireproofing | Cemetitious | ||||||||
King High Line – Intumescent | Structural Steel Fireproofing | Intumescent Paint | ||||||||
Kitchener Auditorium | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Kitchener Memorial Auditorium | Air Barrier & Insulation | Rigid Insulation | ||||||||
Insulation | Glass Mineral Fiber | |||||||||
Kitchener Fire Station #7 | Air Barrier & Insulation | Rigid Insulation | ||||||||
Kolter Office Towers | Air Barrier & Insulation | Rigid Insulation | ||||||||
Lady of Fatima Elementary School | Air Barrier & Insulation | Rigid Insulation | ||||||||
Lakeridge Health Centre | Air Barrier & Insulation | Rigid Insulation | ||||||||
Lakeshore Catholic High School | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Lakeshore Catholic High School – Cecchini | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Lanhack Building – Tarbutt | Structural Steel Fireproofing | Cemetitious | ||||||||
Lansdowne Plaza | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Air Barrier & Insulation | Rigid Insulation | |||||||||
Structural Steel Fireproofing | Cemetitious | |||||||||
Laura Secord Public School | Structural Steel Fireproofing | Cemetitious | ||||||||
Laurentian Public School | Air Barrier & Insulation | Rigid Insulation | ||||||||
Le Germain Hotel | Air Barrier & Insulation | Rigid Insulation | ||||||||
Lewiston-Queenston Bridge | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
LIDAR & Atmospheric Observation | Structural Steel Fireproofing | Cemetitious | ||||||||
Listowel Old Age Home | Cavity Wall Insulation | Glass Fiber | ||||||||
Loblaws – Newmarket | Air Barrier & Insulation | Bakor 021 / Rigid Insulation | ||||||||
London Mental Hospital – D13 | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
London Pump Station | Air Barrier & Insulation | Rigid Insulation | ||||||||
Lookout Point – Fonthill | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Structural Steel Fireproofing | Mineral Fiber | |||||||||
Losani – DeFaveri | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Structural Steel Fireproofing | Cemetitious | |||||||||
Lunnenburg Foundry – Nova Scotia | Insulation | Spray Polyurethane Foam | ||||||||
MacAshphalt Plant | Air Barrier & Insulation | Torch Applied Membrane / Rigid Insulation | ||||||||
Major Ballachey Elementary School | Insulation | Spray Polyurethane Foam | ||||||||
Malvern Park | Structural Steel Fireproofing | Cemetitious | ||||||||
Mammoet | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Mandarin | Structural Steel Fireproofing | Mineral Mineral Fiber | ||||||||
Maple Community Centre | Air Barrier & Insulation | Bakor 06 / Rigid Insulation | ||||||||
Maranatha Gardens – Phase 1 | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Marion Courtyard Residence | Air Barrier & Insulation | Rigid Insulation | ||||||||
Markham YMCA | Air Barrier & Insulation | Rigid Insulation | ||||||||
Mark’s Work Warehouse | Air Barrier & Insulation | Rigid Insulation | ||||||||
Mary Phlealan School | Air Barrier & Insulation | Rubberwall & Rigid Insulation | ||||||||
Air Barrier & Insulation | SA Membrane & Rigid Insulation | |||||||||
McClennan Park | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
McCoy Residence | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
McCormick LTC – London | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
McMaster University | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
McMaster University-Smith Brothers | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
McMaster University Automotive Resource Centre | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
McMaster University – BEAM | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
McMaster University – Bio Med | Structural Steel Fireproofing | Cemetitious | ||||||||
Insulation | Glass Mineral Fiber | |||||||||
McMaster University – Dining Hall | Air Barrier & Insulation | Rigid Insulation | ||||||||
McMaster University – Engineering Graduate Studies | Air Barrier & Insulation | Rigid Insulation | ||||||||
McMaster University – JHE Building Atrium Reno | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
McMaster University – MDLC | Structural Steel Fireproofing | Cemetitious | ||||||||
McMaster University – Ron Joyce Centre | Air Barrier & Insulation | Rigid Insulation | ||||||||
McMaster University – Sick Kids | Structural Steel Fireproofing | Cemetitious | ||||||||
McMaster University – Stair Well | Air Barrier & Insulation | Rigid Insulation | ||||||||
McMaster University – Innovation Park | Air Barrier & Insulation | Rigid Insulation | ||||||||
McMaster University – Student Centre | Air Barrier & Insulation | Rubberwall & Rigid Insulation | ||||||||
Air Barrier & Insulation | SA Membrane & Rigid Insulation | |||||||||
McNeil Coating Pan Addition | Air Barrier & Insulation | Bakor 06 / Spray Polyurethane Foam | ||||||||
Air Barrier & Insulation | Bakor 06 / Rigid Insulation | |||||||||
Millen Road | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Millennium | Air Barrier & Insulation | Rigid Insulation | ||||||||
Milton Hydro Headquarter Renovations | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Milton Memorial Hospital | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Milton Memorial Hospital – PCL | Insulation | Concrete insulated panels | ||||||||
Milton Warehouse – F & M Caulking | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Milton Sports Centre | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Ministry of Natural Resources | Metal Vapour Barrier & Insulation | Bakor 021 / Rigid Insulation | ||||||||
Insulation | Glass Fiber | |||||||||
Structural Steel Fireproofing | Mineral Fiber | |||||||||
Ministry of Transportation | Metal Vapour Barrier & Insulation | Bakor 021 / Rigid Insulation | ||||||||
Insulation | Glass Fiber | |||||||||
Firestop & Smoke Seal | Hilti System | |||||||||
Structural Steel Fireproofing | Mineral Fiber | |||||||||
Mitsui | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
M.K. Rittenhouse | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Mohawk College – Flynn | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Mohawk College – The Joyce Centre for Partnership & Innovation | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Mohawk College – The Joyce Centre for Partnership & Innovation – Ellis Don | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Mountain Co-Op | Air Barrier & Insulation | Rigid Insulation | ||||||||
Mold Masters Arena – GA | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Mold Masters Arena – Melloul Blamey | Structural Steel Fireproofing | Cemetitious | ||||||||
Morrison Street – Niacon | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Mountain Co-Op | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Mount Carmel School – Bromac | Structural Steel Fireproofing | Cemetitious | ||||||||
Myers Road School | Air Barrier & Insulation | Rigid Insulation | ||||||||
National Steel Car | Air Barrier & Insulation | Bakor 021 / Semi-rigid Insulation | ||||||||
NDC – Admin | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
New Apostolic Church | Air Barrier & Insulation | Bakor 06 / Spray Polyurethane Foam | ||||||||
New Apostolic Church – Bramelea | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
New Apostolic Church – Lindsey | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
New Branscombe Health Centre – Brouwer | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
New Branscombe Health Centre – Brouwer | Structural Steel Fireproofing | Cemetitious | ||||||||
New Branscombe – Phoenix Wall Decoration | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
NFBC – Rainbow Bridge Bus Processing Addition | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Structural Steel Fireproofing | Cemetitious | |||||||||
Niagara College – AMIC | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Niagara College – Academic Fitness Addition | Structural Steel Fireproofing | Cemetitious | ||||||||
Niagara College – Simcoe Wing | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Niagara College Campus | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Niagara College (CFWI) | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Niagara College Welland Student Commons | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Niagara Falls CC & Library | Air Barrier & Insulation | Bakor 06 / Spray Polyurethane Foam | ||||||||
North Hamilton Community Centre | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
North Wentworth Community Centre | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Novopharm | Air Barrier & Insulation | Rigid Insulation | ||||||||
Novopharm – Phase II | Air Barrier & Insulation | Rigid Insulation | ||||||||
Oakridge Public School – Bromac | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Oakville Hydro | Structural Steel Fireproofing | Cemetitious | ||||||||
Old Bell Building – 800 King Street | Structural Steel Fireproofing | Cemetitious | ||||||||
Old Fort Erie Interpretive Centre | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Old Virgil Firehll | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Omafra Guelph | Air Barrier & Insulation | Bakor 06 / Bakor 021/Semi-rigid Insulation | ||||||||
Metal Vapour Barrier & Insulation | Torch Applied Membrane / Rigid Insulation | |||||||||
OPP – Burk’s Falls | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
OPP – Chatham | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
OPP Chatham – Bird | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
OPP Kenora | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
OPP Long Sault – Bird | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
OPP – Mount Forest | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
OPP Mount Forest – Bird | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
OPP – North Bay FIU | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
OPP North Bay FIU – Bird | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
OPP North Bay RCC – Bird | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
OPP – North Bay Regional Command Centre | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
OPP Peterborough | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
OPP South Porcupine | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
OPP – Walkerton | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Orangeville Recreation Complex | Air Barrier & Insulation | Rigid Insulation | ||||||||
Outlet Mall – PJ Daly – AVB | Air Barrier & Insulation | Rigid Insulation | ||||||||
Outlet Mall – PJ Daly – Sprayed Foam | Insulation | Spray Polyurethane Foam | ||||||||
Outlet Mall – Phase II | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Our Lady of Lourdes Elementary School | Cavity Wall Insulation | Glass Mineral Fiber | ||||||||
Owen Sound Court House | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Painswick South Municipal Station | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Palermo Medical Centre – GA | Installation | Metal Brick Ties | ||||||||
Palermo Professional Centre-Cooper Construction | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Paramedic | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Parker Controls | Insulation | Glass Mineral Fiber | ||||||||
Patene – Nebo Road | Insulation | Spray Polyurethane Foam | ||||||||
Peerless Machine | Air Barrier & Insulation | Rigid Insulation | ||||||||
Pelham Arena | Commercial Roof System | Membrane – Spray Applied | ||||||||
Pelham Community Centre – Ball | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Structural Steel Fireproofing | Cemetitious | |||||||||
Pelham Community Centre – Cecchini | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Penn Financial | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Penatanguishente Super Jail | Air Barrier & Insulation | Bakor 06 / Bakor 021/Semi-rigid Insulation | ||||||||
Torch Applied Membrane / Rigid Insulation | ||||||||||
Structural Steel Fireproofing | Mineral Fiber | |||||||||
Performance Acura | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Perimeter Institute | Air Barrier & Insulation | Rigid Insulation | ||||||||
Peterborough Operations Centre | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Structural Steel Fireproofing | Cemetitious | |||||||||
Peterborough WWTP | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Petro Canada – Sarnia | Structural Steel Fireproofing | Cemetitious | ||||||||
Air Barrier & Insulation | Spray Polyurethane Foam | |||||||||
Pioneer Park Redevelopment | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Planet Night Club | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Port Colborne OC – Capital Structures | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Port Colborne Operations Centre – JR Certus | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Pottersberg Water Pollution Control Plant | Air Barrier & Insulation | Bakor 021 / Rigid Insulation | ||||||||
Preston High School | Air Barrier & Insulation | Rigid Insulation | ||||||||
Preston Waste Centre Treatment Plant | Air Barrier & Insulation | Bakor 021 / Rigid Insulation | ||||||||
Prince of Wales – Bromac | Structural Steel Fireproofing | Cemetitious | ||||||||
Provincial Court Relocation | Structural Steel Fireproofing | Mineral Fiber | ||||||||
Queensdale | Structural Steel Fireproofing | Cemetitious | ||||||||
Queenston Bridge | Air Barrier & Insulation | Rigid Insulation | ||||||||
Rainville Construction-Quarry Rd. Grimsby | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
RA Farrow Office – Ayr | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Renaissance II | Air Barrier & Insulation | Bakor 06 / Semi-rigid Insulation | ||||||||
Metal Vapour Barrier & Insulation | Torch Applied Membrane / Rigid Insulation | |||||||||
Renison University College | Structural Steel Fireproofing | Cemetitious | ||||||||
Research in Motion – Building C | Air Barrier | Membrane – SA | ||||||||
Richmond Hill – Dineen | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Ricoh Centre | Structural Steel Fireproofing | Cemetitious | ||||||||
Structural Steel Fireproofing | Intermescent | |||||||||
Rosehill – Procon | Structural Steel Fireproofing | Cemetitious | ||||||||
Structural Steel Fireproofing | Intermescent | |||||||||
Firestop & Smokeseal | Hilti System | |||||||||
Ross McDonald School for the Blind | Air Barrier & Insulation | Rigid Insulation | ||||||||
Roy Gordon Research Facility | Air Barrier & Insulation | Bakor 021/Semi-rigid Insulation | ||||||||
Self Applied Membrane / Rigid Insulation | ||||||||||
Royal Connaught Hamilton – Phase I | Structural Steel Fireproofing | Cemetitious | ||||||||
Air Barrier & Insulation | Spray Polyurethane Foam | |||||||||
Royal Connaught Hamilton – Phase II | Structural Steel Fireproofing | Cemetitious | ||||||||
Air Barrier & Insulation | Spray Polyurethane Foam | |||||||||
Ryerson Public School | Air Barrier & Insulation | Rigid Insulation | ||||||||
Sage VI | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Sage VIII | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Saint Mary’s University | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Saint Michaels – Guelph | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Saint Michael’s High School | Structural Steel Fireproofing | Mineral Fiber | ||||||||
Samuel Steel – Abcott | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Sandhill – DeFaveri | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Sandlewood Transit Facility | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Scott Construction – NOTL | Structural Steel Fireproofing | Cemetitious | ||||||||
Sifton – GA London | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Simcoe Affordable Housing – Collingwood | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Sir Adam Beck School | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Skyway WWTP | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Slappendel Greenhouses | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Structural Steel Fireproofing | Thermal Barrier | |||||||||
Smithsonian Institute – National Museum American Indians | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Smithville/West Lincoln Arena – Cecchini | Air Barrier & Insulation | Spray Polyurethane Foam & Rigid insulation | ||||||||
Smithville /West Lincoln Arena – Ball | Structural Steel Fireproofing | Cemetitious | ||||||||
Smithville Christian High School | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Sobey’s Ontario Regional Office – Scorpio | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Solstice Condos | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Southward Community Building | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Southwest Public School | Air Barrier & Insulation | Rigid Insulation | ||||||||
Sport Check | Air Barrier & Insulation | Rigid Insulation | ||||||||
Sport Check II | Air Barrier & Insulation | Rigid Insulation | ||||||||
Sportsworld | Air Barrier & Insulation | Bakor 031 / Rigid Insulation | ||||||||
Sportsworld – Phase II | Air Barrier & Insulation | Rigid Insulation | ||||||||
St. Andrews Terrace | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
St. Anthony’s Parish | Air Barrier & Insulation | Rigid Insulation | ||||||||
St. Barsaumo Syriac Orthodox Church | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
St. Basil’s Rectory | Commercial Roof System | Metal | ||||||||
St. Catharines Performing Arts Centre | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
St. Charles – Cecchini | Air Barrier | Bakor Blueskin | ||||||||
St. Francis Xavier – Tarbitt | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
St Gabriel’s – Cecchini | Air Barrier & Insulation | Rigid Insulation | ||||||||
St. George Quonsit Hut | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
St. Helen’s | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
St. James CES – St. Catharines – Charter | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
St. James School – Cecchini | Air Barrier | Bakor Blueskin | ||||||||
St. Jerome’s University | Air Barrier & Insulation | Semi-Rigid Insulation | ||||||||
St. Johns Killmarnok | Air Barrier & Insulation | Rigid Insulation | ||||||||
St. John’s Catholic School | Air Barrier & Insulation | Semi-Rigid Insulation | ||||||||
St. Joseph’s Ambulatory Care | Air Barrier & Insulation | Bakor 021 / Rigid Insulation | ||||||||
St. Joseph’s Hospital | Air Barrier & Insulation | Bakor 021 / Rigid Insulation | ||||||||
St. Leonard’s Emerald Street | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
St. Martin Elementary School | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
St. Mary’s High School – Kitchener | Air Barrier & Insulation | Bakor 021 / Rigid Insulation | ||||||||
St. Michael’s Elementary School – Stratford | Air Barrier & Insulation | Rigid Insulation | ||||||||
St. Michael’s – Niagara Falls | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Structural Steel Fireproofing | Cemetitious | |||||||||
St. Michael’s – Guelph | Air Barrier & Insulation | Semi-rigid insulation | ||||||||
St Naum Church | Cavity Wall Insulation | Glass Mineral Fiber | ||||||||
St. Paul Elementary | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
St. Peters Hospital – Chedoke Long Term Health Care | Air Barrier & Insulation | Rigid Insulation | ||||||||
St. Stephen of Hungary Parish Hall | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
St. Thomas Elgin General Hospital (STEGH) | Air Barrier & Insulation | Semi-rigid insulation | ||||||||
St. Theresa’s | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Station 15 & 16 – Defaveri | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Staybridge Inn – St. Jacobs | Air Barrier & Insulation | Tyvek & Semi-rigid insulation | ||||||||
Steve Kerr Arena | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Stratford – MCOR Masonry | Air Barrier & Insulation | Rigid Insulation | ||||||||
Stoney Creek Community Centre | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Strathmere Lodge – Strathroy | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Sunnyside Home | Air Barrier & Insulation | Rigid Insulation | ||||||||
Sunnyside Old Age Home | Air Barrier & Insulation | Rigid Insulation | ||||||||
Sydenham Hall Residence Entrance | Air Barrier & Insulation | Rigid Insulation | ||||||||
Swied Addition | Air Barrier & Insulation | Semi-rigid insulation | ||||||||
Table Rock – Merit | Structural Steel Fireproofing | Cemetitious | ||||||||
Target- Back to Basic | Air Barrier & Insulation | Rigid Insulation | ||||||||
Target – Barrie | Air Barrier & Insulation | Rigid Insulation | ||||||||
Target – Chatham | Air Barrier & Insulation | Rigid Insulation | ||||||||
Target – Erin Mills – PJ Daly | Air Barrier & Insulation | Rigid Insulation | ||||||||
Target – Fergus | Air Barrier & Insulation | Rigid Insulation | ||||||||
Target – Hamilton 0 PJ Daly | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Target – Kitchener | Air Barrier & Insulation | Rigid Insulation | ||||||||
Target – Niagara Falls | Air Barrier & Insulation | Rigid Insulation | ||||||||
Target – Oakville – Phase I | Air Barrier & Insulation | Rigid Insulation | ||||||||
Target – Oakville – Phase II | Air Barrier & Insulation | Rigid Insulation | ||||||||
Target – Sheridan Mall – Anco | Air Barrier & Insulation | Rigid Insulation | ||||||||
Target – Sheridan Mall – GA | Air Barrier & Insulation | Rigid Insulation | ||||||||
Target – Sudbury | Air Barrier & Insulation | Rigid Insulation | ||||||||
Target – Thunder Bay | Air Barrier & Insulation | Rigid Insulation | ||||||||
Target – Waterloo | Air Barrier & Insulation | Rigid Insulation | ||||||||
TD Bank | Metal Vapour Barrier & Insulation | Semi-rigid Insulation | ||||||||
TD Centre – F & M | Structural Steel Fireproofing | Cemetitious | ||||||||
Terminal II | Metal Vapour Barrier & Insulation | Rigid Insulation | ||||||||
Terminal III – GTAA | Structural Steel Fireproofing | Mineral Mineral Fiber | ||||||||
Air Barrier & Insulation | Rigid Insulation | |||||||||
The Astra Society of Haliton – St Emerald’s | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
The Britt – Lanterra | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Acoustical – Insulation | Glass Fiber | |||||||||
The Church of Archangel | Air Barrier & Insulation | Rigid Insulation | ||||||||
The Meridian Centre St. Catharines – Ball Rankin | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
The Meridian Centre St. Catharines – GA | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
The Venetian | Structural Steel Fireproofing | Cemetitious | ||||||||
Insulation | Glass Mineral Fiber | |||||||||
Thompson Creek School | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Thompson Road WWTP | Air Barrier | Bakor Blueskin | ||||||||
Thorold Arena | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Thunder Bay Courthouse – D13 | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Thunder Bay Consolidated Courthouse – Bird | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Thunder Bay Courthouse – GA Masonry | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Trent University | Air Barrier & Insulation | Rigid Insulation | ||||||||
Trillium Hospital – Mississauga, Ontario | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Air Barrier & Insulation | Spray Polyurethane Foam | |||||||||
Trillium Insurance – Listowell | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Tora Pharmacy | Air Barrier & Insulation | Rigid Insulation | ||||||||
Toyota – Fort Erie | Structural Steel Fireproofing | Cemetitious | ||||||||
United Lands | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Union Gas Chatham | Air Barrier & Insulation | Rigid Insulation | ||||||||
University of Guelph – Animal Hospital | Air Barrier & Insulation | Rigid Insulation | ||||||||
University of Guelph – Fieldhouse | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
University of Guelph – Harbridge & Cross | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
University of Guelph- Humber Campus | Air Barrier & Insulation | Rigid Insulation | ||||||||
University of Guelph – Konia | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
University of Guelph – Science Complex | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
University of Guelph – W.F. Mitchell Athletic Centre | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
University of Toronto – Gerstein | Air Barrier & Insulation | Rigid Insulation | ||||||||
University of Waterloo | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
University of Waterloo – CEIT | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
University of Waterloo – Pool | Air Barrier & Insulation | Rigid Insulation | ||||||||
University of Waterloo – Quantum Nano | Air Barrier & Insulation | Rigid Insulation | ||||||||
University of Waterloo – Student Life Centre | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
University of Waterloo – DWE – Walter Fedy | Structural Steel Fireproofing | Cemetitious | ||||||||
University of Waterloo – DWE – GA | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
University of Waterloo – Federation Hall | Structural Steel Fireproofing | Cemetitious | ||||||||
University of Western Ontario – Biotron | Air Barrier & Insulation | Rigid Insulation | ||||||||
University of Western Ontario – IRB | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
University Of Western Ontario – Music Hall | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
University of Western Ontario – Spencer Engineering | Air Barrier & Insulation | Rigid Insulation | ||||||||
University of Western Ontario – Windy | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Upper Canada College | Air Barrier & Insulation | Rigid Insulation | ||||||||
Upper Canada Shopping Centre | Structural Steel Fireproofing | Mineral Mineral Fiber | ||||||||
Victoria Senior Centre – Fergus | Structural Steel Fireproofing | Cemetitious | ||||||||
Village by the Arboretum | Air Barrier & Insulation | Bakor 06 / Spray Polyurethane Foam | ||||||||
Violin Addition | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Violin Addition – Phase II | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Virgil Commercial Plaza Phase 2 | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Virgil Commercial Plaza Phase I | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Wal-Mart – Manacore | Structural Steel Fireproofing | Cemetitious | ||||||||
Wal-Mart – Mississauga | Air Barrier & Insulation | Rigid Insulation | ||||||||
Waterloo Administration | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Waterloo Recreation Centre | Air Barrier & Insulation | Rigid Insulation | ||||||||
Waterloo Town Centre | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Waterloo North Hydro | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Waterloo Paramedic – Magill | Structural Steel Fireproofing | Cemetitious | ||||||||
Air Barrier & Insulation | Spray Polyurethane Foam | |||||||||
Waterloo Town Square | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Waterloo WWTF – Contract #3 | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Waterloo WWTF – Contract #4 | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
WCC F and H | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Welland Long Term Care – Brouwer | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Welland LTC – JVC | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Welland Wellness Centre | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Wellesley Public School | Air Barrier & Insulation | Rubberwall & Rigid Insulation | ||||||||
Air Barrier & Insulation | SA Membrane & Rigid Insulation | |||||||||
Wellington Airport | Air Barrier & Insulation | Rigid Insulation | ||||||||
Wellington County Corrections | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Wellington Terrace – Elora | Air Barrier & Insulation | Rigid Insulation | ||||||||
Wellness Suites – DeFaveri | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Structural Steel Fireproofing | Cemetitious | |||||||||
West Oak Secondary School | Air Barrier & Insulation | Rigid Insulation | ||||||||
Western Fair Casino & Racetrack | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Westinghouse – CSL | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Wilfred Laurier University | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Wilfred Laurier University – Academic & Science Building | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Wilfred Laurier University – Dining Hall | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
Wilfred Laurier University – Library | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Wilfred Laurier University – SBE Building | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Wilfred Laurier University – Student Residence | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
William Henry School – Cecchini | Air Barrier & Insulation | Semi-rigid Insulation | ||||||||
William Osler Hospital – F&M Caulking | Structural Steel Fireproofing | Intumescent Paint | ||||||||
William Thomason Student Residence – PJ Daly | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
William Thompson Student Residence – KONIA | Air Barrier & Insulation | Spray Polyurethane Foam | ||||||||
Willow Road School | Air Barrier & Insulation | Rubberwall & Rigid Insulation | ||||||||
Air Barrier & Insulation | SA Membrane & Rigid Insulation | |||||||||
Woodstock Collegiate | Air Barrier & Insulation | Rubberwall & Rigid Insulation | ||||||||
Air Barrier & Insulation | SA Membrane & Rigid Insulation | |||||||||
Woodstock Toyota | Air Barrier & Insulation | Rigid Insulation | ||||||||
YMCA | Insulation | Glass Mineral Fiber | ||||||||
York Regional School Board | Air Barrier & Insulation | Rigid Insulation | ||||||||
Yorkdale Shopping Centre | Acoustic System | Rigid Acoustic Board | ||||||||
Insulation | Glass Mineral Fiber / Rigid Insulation | |||||||||
York University | Structural Steel Fireproofing | Cemetitious | ||||||||
York University | Air Barrier & Insulation | Rigid Insulation | ||||||||
Zeller School | Air Barrier & Insulation | Rubberwall & Rigid Insulation | ||||||||
Air Barrier & Insulation | SA Membrane & Rigid Insulation | |||||||||
Zeller’s Drive Pumping Station | Air Barrier & Insulation | Rigid Insulation |
Projects listed here were Estimated – Projects Managed – Completed by:
Mark Doerrsam, Larry Henderson, Robert Doerrsam or companies affiliated with those individuals